<< Click to Display Table of Contents >> Manual > Monitoring system construction guide > Construction of major functions > Demand monitoring > Manual incorporation of the demand report screen library > Manually importing the demand report screen library |
overview
This section explains how to manually embed a "Demand Report" in the screen library.
If you want to add demand reporting functionality to a standard framework project later, or if you are building your own project and want to incorporate demand reporting, use this procedure as a reference.
|
To use the Demand Report Screen Library, the Demand Monitoring Screen Library must be installed. For instructions on manually installing the Demand Monitoring Screen Library, see "Manual Installation of the Demand Monitoring Screen Library". |
|
The screen library comes with samples. You can open the samples from Panel Editor. For details on how to open the samples, please refer to "Screen Library Help / About Samples". |
Manual inclusion of the Demand Report Screen Library
The following are the steps to manually incorporate a new "Demand Report" into a project that already has the "Demand Monitoring" screen library added. If the Demand Monitoring Screen Library has not yet been incorporated, please incorporate Demand Monitoring by following the steps in "Manually incorporating the Demand Monitoring Screen Library".
■ Work procedure
1.Select Screens Library from the Libraries tab
In Panel Editor, select the Library tab and set the type to "Screen Library".

The display in the center of the screen will then switch to the library selection screen.
2.Importing a "Demand Report" from the Screen Library
Select "Demand Report" from the screen library list and drag and drop it onto "client.xml" in the project tree.

|
Then, a folder called "_DemandSummary" was created as shown on the left, and all the necessary forms were copied as a screen library.
_DemandSummary - Demand report screen set
|
To use the demand report screen library, you need to import the server settings from the sample. For instructions on how to import the server settings, see "Importing Server Settings for Demand Reports".
3.Describe the screen call process
After embedding a form from the screen library, implement the process to call the screen from the library.
There are several ways to call up screens from the Screen Library. For details on how to call up screens, please refer to "Calling Screens from the Screen Library" in the Screen Creation Guide.